Date | Location | Type | Details |
---|---|---|---|
June 2 - late Summer | 102 St between 111 and 113 avenues | Full closure | Full road reconstruction with new underground utilities, sidewalks and streetlights as part of the 102 Street project. |
July - late Summer | 89 Ave between 81a and 86 streets | Partial closure | Full road reconstruction with new underground utilities, sidewalks and streetlights as part of the 89 Avenue project. Access to the Evangelical Church and Duncan Cran School from will be from the east. |
July 14 - late Summer | 89 Ave between Cree Road and 107 Street | Partial closure | Full road reconstruction with new underground utilities, sidewalks and streetlights as part of the 89 Avenue project. |
August 20 - October 10 | 93 Avenue east of 86 St | Partial closure | Private contractor upgrading underground utilities. |
September 22 - October 2 | 100 Avenue between 102 and 104 streets | Partial closure | Contractor replacing sidewalk. |
September 18 - October 3 | 86 Street Frontage north of 91 avenue | Full closure | Private contractor installing underground utilities. Access from alley. |
September 28 | Alaska Road South near 104 Street | Partial closure | Crews repairing manhole covers. |
October 1 | 96 Avenue between 82 and 84 streets | Full closure | Crews repairing underground utilities. |
October 1 & 2 | 100 Avenue east of 86 Street | Partial closure | Crews cleaning ditches. |