City capital projects are long‑term investments in the infrastructure, facilities, and services that support daily life in Fort St. John. These projects help maintain and improve infrastructure such as roads, sidewalks, parks, buildings, water and sewer systems, and City equipment, while supporting growth, safety, and long‑term sustainability.
Visit the Completed Capital Projects page to view recently completed projects.
Capital Project Listing
101 Avenue
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Fall 2026
Budget
$2 million | Funded by the Peace River Agreement and Water and Sewer Reserves
Project Description
Rebuilding 101 Avenue from 104 to 106 streets.
Status
Pre-construction
102 Street - Phase 2
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Summer 2026
Budget
$2.3 million | Funded by the Peace River Agreement and Water and Sewer Reserves
Project Description
Rebuilding 102 Street from 109 to 111 avenues.
Status
Under construction
104 Street
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Summer 2026
Budget
$1.6 million | Funded by the Peace River Agreement and Water Reserves
Project Description
Rebuilding 104 Street from 108 to 111 avenues.
Status
Under construction
106 Street Water Reservoir Replacement
Category
Water & Sewer
Start date
Spring 2026
End date
Spring 2027
Budget
$8.5 million | Funded by Growing Communities Fund and Water Reserves
Project Description
Construction of a new water reservoir near the existing 106 Street reservoir.
Status
Under construction
99 Avenue
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Fall 2026
Budget
$2.24 million | Funded by the Peace River Agreement and Sewer Reserves
Project Description
Rebuilding 99 Avenue from 98 to 100 streets.
Status
Pre-construction
Bouffioux Coulee – Lower Bank Armouring Replacement
Category
Roads & Related Infrastructure
Start date
Summer 2025
End date
Fall 2026
Project Description
To protect the City’s sanitary infrastructure, the treated sewage effluent pipe that discharges to the Peace River needs to be defended from further erosion due to stormwater flow in Bouffioux Creek.
Status
Design and Permitting
Major Sidewalk Improvements
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Fall 2026
Budget
$840,000 | Funded by the Peace River Agreement
Project Description
Replacement of several sidewalks across the community.
Status
Pre-construction
Peace River Road
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Fall 2026
Budget
$3.75 million | Funded by the Peace River Agreement and Water and Sewer Reserves
Project Description
Rebuilding Peace River Road from 110 to 112 avenues.
Status
Pre-construction
Road Overlay Program - 2026
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Fall 2026
Budget
$3 million | Funded by the Peace River Agreement
Project Description
Repaving multiple blocks of roads throughout the community.
Status
Pre-construction
Sanitary Sewer Upgrades - 2026
Category
Roads & Related Infrastructure
Start date
Spring 2026
End date
Fall 2026
Budget
$1.2 million | Funded by Sewer Reserves
Project Description
Installation of a new sanitary sewer line in the Mathews Park area and replacement of a sanitary sewer line on 112 Street.
Status
Pre-construction