Start date
Summer 2023
End date
Late Spring 2024
Status
Complete
Budget
$2.25 million | Funded by the Peace River Agreement and Water and Sewer Reserves
Project Description
Upgrades to the underground utilities, installation of new sidewalks and streetlighting, and a complete rebuild of the road along 89 Avenue. Phase 1 will see between 78a and 81a streets completed.