Capital Projects

  1. 100 Street - CN Crossing

    Category: Roads & Related Infrastructure

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $1 million

    Project Description: Installation of storm main crossing under CN railway on 100 Street.

    Project Status: In Progress

  2. 100 Street 4-laning - Phase 3

    Category: Roads & Related Infrastructure

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget:

    Project Description: The final phase of 4-laning of 100 Street between 110 Avenue and East Bypass Road.

    Project Status: Project tendering

  3. 86 Street Frontage

    Category: Roads & Related Infrastructure

    Start Date: Summer 2018

    End Date: Fall 2019

    Budget: $1.5 million

    Project Description: Frontage road upgrades from 93 to 98 Avenue including paving of gravel surface and installation of a storm main and streetlights.

    Project Status: In Progress

  4. 92A Street

    Category: Roads & Related Infrastructure

    Start Date: Summer 2018

    End Date: Fall 2019

    Budget: $5.3 million

    Project Description: 92A Street road reconstruction from 89 to 94 Avenue.

    Project Status: In Progress

  5. 93 Avenue Sanitary Sewer Upgrades

    Category: Water & Sewer

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $500,000

    Project Description: Construction of upgraded sanitary sewer systems to alleviate potential sanitary sewer flooding.

    Project Status: Construction staging

  6. Centennial Park

    Category: Facilities, Buildings & Parks

    Start Date: Summer 2018

    End Date: Fall 2019

    Budget: $5.5 million

    Project Description: Centennial Park redevelopment including new band shell, picnic shelter, grading and earthworks, hardscape and softscape construction and two new playgrounds.

    Project Status: In Progress

  7. Curling Club Lighting Upgrades

    Category: Facilities, Buildings & Parks

    Start Date: Summer 2019

    End Date: Summer 2019

    Budget: $33,000

    Project Description: Replace existing interior lighting with LED lights.

    Project Status: Construction staging

  8. Indoor Play Structure

    Category: Facilities, Buildings & Parks

    Start Date: Fall 2018

    End Date: Spring 2019

    Budget: $65,000

    Project Description: To expand available activities by installing a small play structure for kids to play on and burn off energy when they are in the Pomeroy Sport Centre.

    Project Status: In Progress

  9. Kids Arena Fieldhouse Lighting Upgrades

    Category: Facilities, Buildings & Parks

    Start Date: Summer 2019

    End Date: Summer 2019

    Budget: $88,000

    Project Description: Replace interior lighting with energy efficient LED lights.

    Project Status: Construction staging

  10. Tahltan Road

    Category: Water & Sewer

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $1.25 million

    Project Description: Installation of water and sanitary sewer main on the extension of Tahltan Road west of Old Fort Road through Local Area Servicing Agreement.

    Project Status: In Progress

  11. Tahltan Road Extension

    Category: Roads & Related Infrastructure

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $5.25 million

    Project Description: The final phase for construction of the extension of Tahltan Road from the Old Fort Road to the 242 Road.

    Project Status: Construction staging

  12. Toboggan Hill Off-Leash Dog Park

    Category: Facilities, Buildings & Parks

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $706,000

    Project Description: A 9-acre fenced and landscaped off-leash dog park and an expanded parking lot.

    Project Status: In progress

  13. Water Recovery Facility

    Category: Water & Sewer

    Start Date: Summer 2017

    End Date: Fall 2019

    Budget: $9.5 million

    Project Description: Upgrades to allow the use of treated effluent.

    Project Status: In progress