Water & Sewer
-
103 Avenue Watermain
Start Date: Spring 2023
End Date: Summer 2023
Budget: $1,000,000 | Funded by Water Reserves
Project Description: Installation of a new watermain and additional fire hydrants along 103 Avenue between 96 and 98 streets.
Project Status: Under construction
-
93 Street Sanitary Extension
Start Date: Spring 2023
End Date: Summer 2023
Budget: $870,000 | Funded by Sewer Reserves
Project Description: Extend and connect the sanitary sewer system along 93 Street between 112 and 115 avenues to increase capacity.
Project Status: Pre-construction