Completed Projects

  1. 100 Street - CN Crossing

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $1 million

    Project Description: Installation of storm main crossing under CN railway on 100 Street.

    Project Status: Completed

  2. 100 Street 4-laning - Phase 3

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $5.8 million

    Project Description: The final phase of 4-laning of 100 Street between 110 Avenue and Northern Lights Drive.

    Project Status: Completed

  3. 101 Avenue

    Start Date: Summer 2019

    End Date: Fall 2019

    Budget: $1.5 million

    Project Description: Completed

    Project Status: Upgrade the existing gravel road to a paved surface including storm sewer, sidewalk, street lighting, and trail installation.

  4. 113 Avenue

    Start Date: Spring 2019

    End Date: Summer 2019

    Budget: $1.5 million

    Project Description: Replacement of aging water main and reconstruction of the road with street lighting and a sidewalk.

    Project Status: Completed

  5. 83 Street

    Start Date: Fall 2018

    End Date: Fall 2019

    Budget: $1.7 million

    Project Description: Construction of 83 Street north of 112 Avenue with sidewalk, trail, and street lights. Also includes intersection upgrades on 112 Avenue.

    Project Status: Completed

  6. 86 Street Frontage

    Start Date: Spring 2018

    End Date: Fall 2019

    Budget: $1.5 million

    Project Description: Frontage road upgrades from 93 to 98 Avenue including paving of gravel surface and installation of a storm main and streetlights.

    Project Status: Completed

  7. 87 Avenue

    Start Date: Summer 2019

    End Date: Fall 2019

    Budget: $1.2 million

    Project Description: Upgrading the existing gravel street to a paved road.

    Project Status: Completed

  8. 92A Street - Phase 1

    Start Date: Summer 2018

    End Date: Fall 2019

    Budget: $5.3 million

    Project Description: 92A Street road reconstruction from 89 to 94 Avenue.

    Project Status: Completed

  9. 93 Avenue Sanitary Sewer Upgrades

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $500,000

    Project Description: Construction of upgraded sanitary sewer systems to alleviate potential sanitary sewer flooding.

    Project Status: Completed

  10. 98 Street Signalization

    Start Date: Fall 2019

    End Date: Winter 2020

    Budget: $500,000

    Project Description: This project will signalize the intersection at 98 Street and 100 Avenue and include lane upgrades.

    Project Status: Completed

  11. Curling Club Lighting Upgrades

    Start Date: Summer 2019

    End Date: Summer 2019

    Budget: $33,000

    Project Description: Replace existing interior lighting with LED lights.

    Project Status: Completed

  12. Indoor Play Structure

    Start Date: Fall 2018

    End Date: Spring 2019

    Budget: $65,000

    Project Description: To expand available activities by installing a small play structure for kids to play on and burn off energy when they are in the Pomeroy Sport Centre.

    Project Status: Completed

  13. Kids Arena Fieldhouse Lighting Upgrades

    Start Date: Summer 2019

    End Date: Summer 2019

    Budget: $88,000

    Project Description: Replace interior lighting with energy efficient LED lights.

    Project Status: Completed

  14. RV Sani-Dump

    Start Date: Summer 2019

    End Date: Fall 2019

    Budget: $500,000

    Project Description: The expansion of the current RV Sani-Dump facilities to provide additional service bays.

    Project Status: Completed

  15. Tahltan Road

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $1.25 million

    Project Description: Installation of water and sanitary sewer main on the extension of Tahltan Road west of Old Fort Road through Local Area Servicing Agreement.

    Project Status: Completed

  16. Tahltan Road Extension

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $5.25 million

    Project Description: The final phase for construction of the extension of Tahltan Road from the Old Fort Road to the 242 Road.

    Project Status: Completed