Roads & Related Infrastructure
-
100 Street Corridor - Phase 1
Start Date: Spring 2020
End Date: Fall 2020
Budget: $4.24 million
Project Description: The first phase of the project includes upgrades to the intersection at 100 Street and 96 Avenue and various other improvements to support future phases.
Project Status: Under Construction
-
104 Street
Start Date: Summer 2020
End Date: Fall 2020
Budget: $1.01 million
Project Description: Local Area Service project on 104 Street between 95 Avenue to 97 Avenue to upgrade an existing gravel road to paved standards including storm sewer and street lighting.
Project Status: Under Construction
-
91 Avenue
Start Date: Summer 2020
End Date: Fall 2020
Budget: $1.35 million
Project Description: Local Area Service project on 91 Avenue between 107 Street and 109 Street to upgrade an existing gravel road to paved standards including storm sewer and street lighting.
Project Status: Under Construction
-
92A Street - Phase 2
Start Date: Spring 2020
End Date: Fall 2020
Budget: $1.75 million
Project Description: This is the last major component of the Stormwater Master Plan and will include installation of storm sewer systems, rebuilding the road and improvements to sidewalks, trails and street lighting.
Project Status: Under Construction
-
96 Street - Lighting
Start Date: Spring 2020
End Date: Summer 2020
Budget: $800,000
Project Description: Installation of traffic signals at 96 Street and 96 Avenue and upgrades to street lighting along 96 Street.
Project Status: Completed