Completed Projects

  1. 100 Street - CN Crossing

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $1 million

    Project Description: Installation of storm main crossing under CN railway on 100 Street.

    Project Status: Completed

  2. 100 Street 4-laning - Phase 3

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $5.8 million

    Project Description: The final phase of 4-laning of 100 Street between 110 Avenue and Northern Lights Drive.

    Project Status: Completed

  3. 101 Avenue

    Start Date: Summer 2019

    End Date: Fall 2019

    Budget: $1.5 million

    Project Description: Completed

    Project Status: Upgrade the existing gravel road to a paved surface including storm sewer, sidewalk, street lighting, and trail installation.

  4. 101 Street - Phase 1

    Start Date: Spring 2020

    End Date: Summer 2020

    Budget: $375,000

    Project Description: Local Area Service project to bring the existing gravel road to paved standards. Phase one is the installation of the storm sewer system, while phase two, scheduled for 2021, is to pave the road.

    Project Status: Completed

  5. 113 Avenue

    Start Date: Spring 2019

    End Date: Summer 2019

    Budget: $1.5 million

    Project Description: Replacement of aging water main and reconstruction of the road with street lighting and a sidewalk.

    Project Status: Completed

  6. 83 Street

    Start Date: Fall 2018

    End Date: Fall 2019

    Budget: $1.7 million

    Project Description: Construction of 83 Street north of 112 Avenue with sidewalk, trail, and street lights. Also includes intersection upgrades on 112 Avenue.

    Project Status: Completed

  7. 86 Street Frontage

    Start Date: Spring 2018

    End Date: Fall 2019

    Budget: $1.5 million

    Project Description: Frontage road upgrades from 93 to 98 Avenue including paving of gravel surface and installation of a storm main and streetlights.

    Project Status: Completed

  8. 87 Avenue

    Start Date: Summer 2019

    End Date: Fall 2019

    Budget: $1.2 million

    Project Description: Upgrading the existing gravel street to a paved road.

    Project Status: Completed

  9. 92A Street - Phase 1

    Start Date: Summer 2018

    End Date: Fall 2019

    Budget: $5.3 million

    Project Description: 92A Street road reconstruction from 89 to 94 Avenue.

    Project Status: Completed

  10. 93 Avenue Sanitary Sewer Upgrades

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $500,000

    Project Description: Construction of upgraded sanitary sewer systems to alleviate potential sanitary sewer flooding.

    Project Status: Completed

  11. 98 Street Signalization

    Start Date: Fall 2019

    End Date: Winter 2020

    Budget: $500,000

    Project Description: This project will signalize the intersection at 98 Street and 100 Avenue and include lane upgrades.

    Project Status: Completed

  12. Centennial Park

    Start Date: Summer 2018

    End Date: Summer 2020

    Budget: $5.5 million

    Project Description: Centennial Park redevelopment including new band shell, picnic shelter, grading and earthworks, hardscape and softscape construction and two new playgrounds.

    Project Status: Completed

  13. Curling Club Lighting Upgrades

    Start Date: Summer 2019

    End Date: Summer 2019

    Budget: $33,000

    Project Description: Replace existing interior lighting with LED lights.

    Project Status: Completed

  14. Indoor Play Structure

    Start Date: Fall 2018

    End Date: Spring 2019

    Budget: $65,000

    Project Description: To expand available activities by installing a small play structure for kids to play on and burn off energy when they are in the Pomeroy Sport Centre.

    Project Status: Completed

  15. Kids Arena Fieldhouse - Parking Lot Paving

    Start Date: Summer 2020

    End Date: Summer 2020

    Budget: $400,000

    Project Description: Repaving the Parking Lot behind the Kids Arena Fieldhouse.

    Project Status: Completed

  16. Kids Arena Fieldhouse - Turf

    Start Date: Summer 2020

    End Date: Summer 2020

    Budget: $250,000

    Project Description: Installation of replacement turf field and roof netting in the Kids Arena Fieldhouse.

    Project Status: Completed

  17. Kids Arena Fieldhouse Lighting Upgrades

    Start Date: Summer 2019

    End Date: Summer 2019

    Budget: $88,000

    Project Description: Replace interior lighting with energy efficient LED lights.

    Project Status: Completed

  18. RV Sani-Dump

    Start Date: Summer 2019

    End Date: Fall 2019

    Budget: $500,000

    Project Description: The expansion of the current RV Sani-Dump facilities to provide additional service bays.

    Project Status: Completed

  19. Tahltan Road

    Start Date: Fall 2018

    End Date: Summer 2019

    Budget: $1.25 million

    Project Description: Installation of water and sanitary sewer main on the extension of Tahltan Road west of Old Fort Road through Local Area Servicing Agreement.

    Project Status: Completed

  20. Tahltan Road Extension

    Start Date: Spring 2019

    End Date: Fall 2019

    Budget: $5.25 million

    Project Description: The final phase for construction of the extension of Tahltan Road from the Old Fort Road to the 242 Road.

    Project Status: Completed