  1. 100 Street Corridor - Phase 1

    Category: Community

    Start Date: Spring 2020

    End Date: Fall 2020

    Budget: $4.24 million

    Project Description: The first phase of the project includes upgrades to the intersection at 100 Street and 96 Avenue and various other improvements to support future phases.

    Project Status: Complete

  2. 100 Street Corridor - Phase 2

    Category: Community

    Start Date: May 6, 2021

    End Date: Fall 2021

    Budget: $7.63 million

    Project Description: The second phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 96 Avenue and 99 Avenue.

    Project Status: Completed

  3. 100 Street Corridor - Phase 3

    Category: Community

    Start Date: Spring 2022

    End Date: Fall 2022

    Budget: $9.6 million | Funded by Peace River Agreement and Water & Sewer Reserves

    Project Description: The third phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 99 Avenue and 101 Avenue.

    Project Status: Completed

  4. 100 Street Corridor - Phase 4

    Category: Community

    Start Date: April 11, 2023

    End Date: Fall 2023

    Budget: $8.23 million | Funded by the Peace River Agreement and Water and Sewer Reserves

    Project Description: The fourth phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 101 Avenue and 103 Avenue.

    Project Status: Complete

  5. 100 Street Corridor - Phase 5

    Category: Community

    Start Date: April 15, 2024

    End Date: Fall 2024

    Budget: $9.75 million | Funded by the Peace River Agreement and water and sewer reserves

    Project Description: Pre-construction

    Project Status: The fifth and final phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 103 Avenue and 105 Avenue.

  6. 103 Avenue Watermain

    Category: Community

    Start Date: Spring 2023

    End Date: Summer 2023

    Budget: $1,000,000 | Funded by Water Reserves

    Project Description: Installation of a new watermain and additional fire hydrants along 103 Avenue between 96 and 98 streets.

    Project Status: Complete

  7. 108 Street

    Category: Community

    Start Date: Summer 2023

    End Date: Summer 2023

    Budget: Funded by Developer Holdbacks

    Project Description: Complete construction of 108 Street at 114a Avenue that the developer did not complete, with a paved road surface, sidewalks and streetlighting.

    Project Status: Under construction

  8. 82 Street

    Category: Community

    Start Date: Summer 2023

    End Date: Fall 2023

    Budget: $1.25 million | Funded by the Peace River Agreement and Water Reserves

    Project Description: Upgrade the existing gravel road from 100 to 101 avenues to paved standards with street lighting, sidewalks, and reconstruction of the road base.

    Project Status: Under construction

  9. 89 Avenue - Phase 1

    Category: Community

    Start Date: Summer 2023

    End Date: Late Spring 2024

    Budget: $2.25 million | Funded by the Peace River Agreement and Water and Sewer Reserves

    Project Description: Upgrades to the underground utilities, installation of new sidewalks and streetlighting, and a complete rebuild of the road along 89 Avenue. Phase 1 will see between 78a and 81a streets completed.

    Project Status: Under construction

  10. 93 Street Sanitary Extension

    Category: Community

    Start Date: Summer 2023

    End Date: Summer 2023

    Budget: $870,000 | Funded by Sewer Reserves

    Project Description: Extend and connect the sanitary sewer system along 93 Street between 112 and 115 avenues to increase capacity.

    Project Status: Complete

  11. Charlie Lake Boat Launch Upgrades

    Category: Community

    Start Date: TBA

    End Date: TBA

    Budget:

    Project Description: Upgrades and repairs to the Charlie Lake Boat Launch. An application has been submitted to the Ministry of Water, Land and Resource Stewardship before the work can begin.

    Project Status: Pre-construction

  12. Kids Arena Fieldhouse Upgrades

    Category: Community

    Start Date: Fall 2022

    End Date: Spring 2023

    Budget: $1.2 million | Funded by the Peace River Agreement

    Project Description: Renovations of washrooms, main floor concession and upstairs meeting room, including an accessible lift and new fire alarm system.

    Project Status: Complete

  13. Kin Park Upgrades - Pavilion Building

    Category: Community

    Start Date: Fall 2021

    End Date: Spring 2023

    Budget: $1.89 million | Funded by the Peace River Agreement

    Project Description: Construction of a gathering space, containing a warming area and storage and washroom facilities.

    Project Status: Complete

  14. North Peace Arena Upgrades

    Category: Community

    Start Date: Spring 2022

    End Date: Fall 2022

    Budget: $1.96 million | Funded by the Peace River Agreement and Investing in Canada Infrastructure Program

    Project Description: Upgrades to the North Peace Arena include replacing the roof, installing new air handling units and rooftop exhaust fans, and converting lighting to energy-efficient LED lights.

    Project Status: Complete

  15. RCMP Detachment

    Category: Community

    Start Date: Spring 2020

    End Date: Summer 2023

    Budget: $51.4 million

    Project Description: The new Royal Canadian Mounted Police Detachment, being constructed just north of the current detachment, will house both municipal and provincial funded RCMP units and support staff. The Net-Zero Ready, 3-storey building will utilize BC-sourced Nail Laminated Timber, and allows the City to showcase our commitment to energy conservation and innovative building practices.

    Project Status: Complete

  16. Sidewalks & Streetlighting

    Category: Community

    Start Date: Spring 2023

    End Date: Summer 2023

    Budget: $800,000 | Funded by the Canada Community-Building Fund

    Project Description: Completing the project started last year to install sidewalks and streetlights along 84 Street between 93 and 96 avenues and along 95 Avenue between 84 and 86 streets.

    Project Status: Under construction

  17. Surerus Park - Pitch Redevelopment

    Category: Community

    Start Date: Spring 2022

    End Date: Spring 2023

    Budget: $1.37 million | Funded by the Peace River Agreement

    Project Description: This project will see the two existing pitches in Surerus Park completely rebuilt with improved sub-grade, draining and irrigation.

    Project Status: Under construction

  18. The Station Repairs

    Category: Community

    Start Date: Spring 2023

    End Date: Summer 2023

    Budget: Funded by Developer Holdbacks

    Project Description: Complete construction deficiencies in The Station area that were not completed by the developer, including repairs to concrete and asphalt.

    Project Status: Complete